Back to Top

Subscribe to INSIGHT

Expanding perspectives every month.

Subscribe
<em>Spotlight on Lessons Learned:</em> Project Management Lessons Learned on a Fast Track Engine Test

Accepting a task to perform a fast-track engine test prior to fully understanding its risks and challenges led to cost and schedule issues.

In February 2003, the White Sands Test Facility (WSTF) Propulsion Test Office accepted a task authorized through a Space Act Agreement to perform a rocket engine test for a private company by July 2003. While there were no real technical issues associated with the testing to be performed, there were certain aspects of the test program that were slightly different than the majority of testing performed at WSTF. The differences included high propellant inlet pressures, very short-duration firing pulse widths, and high accuracy propellant flowrate measurements for the short-duration firings.

The technical challenges associated with the test program drove design and fabrication of additional test systems to support the program, mainly propellant delivery systems that operated at pressures higher than typically used at WSTF as well as incorporation of accurate flow measurement devices using technology also not typically used at WSTF. Compounding the technical challenges were other issues such as heavy workload of NASA and contractor project managers, a short timeframe in which to complete testing in order to not impact other tests in the area, and a new and relatively inexperienced staff of project engineers.

Cost and schedule for design, fabrication and checkout were greatly underestimated. The project was successful in terms of completing the testing and delivering the requested data to the customer, but the project was significantly over budget.

Lesson Number: 1394
Lesson Date: April 2, 2004
Submitting Organization: White Sands Test Facility

 

HIGHLIGHTS

LESSONS LEARNED

  • All risks and assumptions should be fully understood and consensus or agreement reached with the customer before committing to any project schedule or budget.

RECOMMENDATIONS

  • From the perspective of the project manager, all available financial and schedule/task-related data must be fully assessed and reviewed as soon as available in order to determine whether project issues are present.
  • It is important to include a detailed risk analysis as part of the project plan in order to flesh out technology or personnel issues and challenges, and to develop a plan to mitigate those risks.

Consult the lesson learned for complete lists.

 

Read the full lesson learned.

Spotlight on Lessons Learned is a monthly series of articles that feature a valuable lesson along with perspective from NASA’s knowledge management community on why the lesson is important. The full lessons are publicly available in NASA’s Lessons Learned Information System (LLIS).

If you have a favorite NASA lesson learned that belongs in the spotlight, please contact us and be sure to include the LLIS Lesson Number.

About the Author

Share With Your Colleagues