Back to Top
<em>Spotlight on Lessons Learned:</em> SAC-D DC/DC Converter On-orbit Failures Likely due to Over-testing Prior to Usage

An international Earth-observing mission to study the salinity of the ocean surface ended in 2015 when an essential part of the spacecraft’s power and attitude control system stopped operating due to over-testing prior to launch. 

The Aquarius/Satélite de Aplicaciones Científicas (SAC)-D satellite observatory, a collaboration between NASA and the Space Agency of Argentina with participation from Brazil, Canada, France and Italy, had a mission-ending failure related to power supply electronics approximately four years after launch. The Aquarius instrument had completed its primary three-year mission and successfully achieved its science objectives as a pathfinder mission to demonstrate that accurate, scientifically significant measurements of salinity could be made from space.

In preparation for the mission, commercial DC/DC converters were tested to the full levels of MIL-PRF-38534, the General Specification for Hybrid Microcircuits, without consideration of the parts’ data sheet limitations. The testing levels not only greatly exceeded the data sheet limit for the parts but were orders of magnitude greater than any levels that could be encountered in the mission. The converters passed the screens and were incorporated into flight hardware, but the parts had been overstressed during testing – ultimately prompting failures on orbit and resulting in the end of the mission. 

 

Lesson Number: 30601
Lesson Date: June 1, 2011
Submitting Organization: Goddard Space Flight Center

 

HIGHLIGHTS

LESSON LEARNED

  • Testing (screening) parts to stress levels well above the application and close to or above the specification limits for an extended period of time may substantially reduce the lifetime of the parts with minimal benefit.
  • Prior to performing either application or data sheet overstress to parts for screening purposes, the risk of overstress to the parts in the project context should be evaluated and captured.

RECOMMENDATIONS

  • Carefully consider the relevance and compatibility – with the manufacturer in the loop – when applying MIL-SPEC screening and qualification processes to COTS parts.
  • Avoid applying screening levels that greatly exceed the mission application (survival) requirements as in many cases such testing will unnecessarily increase risk or reduce the lifetime of the parts.

Consult the lesson learned for complete lists.

 

Jesse Leitner Credit: NASA

Jesse Leitner
Credit: NASA

NASA Goddard Space Flight Center Chief Engineer for Safety and Mission Assurance Jesse Leitner on the importance of this lesson learned:

NASA engineers want a lot of margin and so we have a tendency to over-test things in general without thinking of the implications. And we tend to overly follow some of the rules without thinking about the risk they bring. We especially need to think about the implications of extreme levels of tests. For example, MIL-PRF-38534 demands a 3000g constant acceleration test, which was performed on the Aquarius parts as a screen, even when the part’s data sheet indicated a tolerance to 500g acceleration. 3000g is horrendous and should be challenged every time it’s required.

As we transition to the use of new parts and technologies and more use of commercial parts and other approaches to electronic parts, we really have to understand that different rules apply. Before we start to test the components or the parts that we’re using, we really should understand what their data sheets and specifications say and make sure that we’re not going to over-test them or test them outside of their bounds. There are times when it’s appropriate to test things outside of their bounds, but you have to understand the risks of doing so and you have to acknowledge that you’re doing that.

It’s happened a lot in new EEE parts where we can sometimes blindly follow the specifications when we’re testing parts just because it says in the rule that you’re going to test to these levels. We sometimes do the testing rather than look carefully at what the limitations are and whether the tests at that level are necessary at all. It doesn’t mean it actually is appropriate for your application and that you might not be causing damage to the part and removing its reliability. I like to use a phrase that, ‘You can’t screen reliability into a part, but you can certainly screen it out.’ That’s the danger of testing things outside of the limits of a component that you have and likewise unnecessarily testing things at levels that are not relevant to your application. And this doesn’t just go with parts; this goes with anything.

 

Related Resources

International Spacecraft Carrying NASA’s Aquarius Instrument Ends Operations

Information on Military Specifications for DC/DC Converters

 

Read the full lesson learned.

 

Spotlight on Lessons Learned is a monthly series of articles featuring a valuable lesson along with perspective from a NASA technical expert on why the lesson is important. The full lessons are publicly available in NASA’s Lessons Learned Information System (LLIS).

If you have a favorite NASA lesson learned that belongs in the spotlight, please contact us and be sure to include the LLIS Lesson Number.

About the Author

Share With Your Colleagues